SECTION 1.                 EXECUTIVE SUMMARY

 

Background

 

The residents in the Mines Road and SH 359 planning areas are not provided water service by any water purveyor.  Some residents utilize individual wells that only produce non-potable water.  Most lots within the planning areas are not large enough (considering the existence of numerous dwellings per lot) to accommodate the construction of on-site sewage facilities and private water wells while still maintaining the minimum separation requirements.  Residents must rely on external sources for their potable water needs.

 

The residents in both planning areas do not have access to a centralized wastewater system.  All of the residents utilize some type of on-site system as their primary means of wastewater disposal.  As a whole, these on-site systems are substandard and include undersized and poorly constructed septic systems, pit privies, and open cesspools.  Numerous makeshift gray water systems are also present in both planning areas, which discharge laundry and kitchen wastewater to the ground surface in an effort to minimize the hydraulic loading on the existing septic tank systems.

 

The current number of households and population for the fifteen colonias in 2000 is 787 and 3,725, respectively.  The proposed water and wastewater improvements are designed to provide adequate water and sewer service to the Year 2016 for 1,193 households and 5,649 colonia residents.

 

In addition to the Texas Water Development Board (TWDB) – Economically Distressed Areas Program (EDAP) funding, additional funding for the project will be obtained from Webb County and the North America Development Bank (NADBank).  Using NADBank as a source of funds for the water and wastewater improvements was recognized due to the TWDB limitations associated with the cost per connection. Additionally, the TWDB made a determination that On-Site Systems could be used for all of the colonias in the Mines Road Planning Area; however, a conventional wastewater collection and treatment system is recommended for four of the five Mines Road colonias for long-term sustainability.

 

Obtaining a source of funding from NADBank is critical to ending the continuing health risk posed by the present use of inadequate septic tanks or cesspools as noted by the Texas Natural Resources Conservation Commission (TNRCC) Nuisance Finding (Appendix C).  Adding new connections to the utility system will also provide additional revenues to meet the debt service obligations incurred by the TWDB-EDAP Project (approximately $1.5 million loan to City of Laredo).

 

The City of Laredo defined the concept and the monetary requirements for implementation of the water and wastewater improvements.  The outline of the needs and the funding required was submitted as a Step 1 Format to the Border Environment Cooperation Commission (BECC) on April 8, 1999.  A summary of the proposed project costs by sources and uses is shown in Table 1.

 

TABLE 1

COSTS OF PROPOSED PROJECT and SOURCES and USES OF FUNDS

FUNDING AGENCY

 

TOTAL COST ($'s)

 

WASTEWATER DESCRIPTIONS

 

TWDB-EDAP

LOS CORRALITOS ON-SITE SYSTEMS

$128,850

TWDB-EDAP - *

SH 359 AREA WW COLLECTION LESS LOS TANQUECITOS

$5,755,656

WEBB COUNTY

LOS TANQUECITOS 1 WW COLLECTION

$527,415

NADBANK - **

MINES ROAD AREA WW COLLECTION / TREATMENT LESS LOS CORRALITOS

$4,627,150

 

TOTAL COSTS FOR WASTEWATER IMPROVEMENTS

$11,039,071

 

 

 

 

 

 

 

WATER DESCRIPTIONS

 

TWDB-EDAP

MINES ROAD AREA WATER DISTRIBUTION LESS LOS CORRALITOS

$2,891,314

TWDB-EDAP - *

SH 359 AREA WATER DISTRIBUTION LESS 16" WATER LINE

$5,963,017

WEBB COUNTY

LOS CORRALITOS

$83,560

NADBANK - **

16" WATER LINE ALONG SH 359

$1,604,300

 

TOTAL COSTS FOR WATER IMPROVEMENTS

$10,542,191

 

 

 

 

 

 

 

SUMMARY OF WATER AND WASTEWATER COSTS

 

TWDB-EDAP - *

MINES ROAD AND SH 359 PROJECT AREA, LESS NADBANK & COUNTY

$14,738,837

WEBB COUNTY

LOS TANQUECITOS 1 – WW COLLECTION AND LOS CORRALITOS – WATER

$610,975

NADBANK - **

MINES ROAD – WW COLLECTION, 16" WATER LINE & ALL SERVICE CONNECTIONS

$6,231,450

 

TOTAL PROJECT COSTS FOR WATER AND WASTEWATER IMPROVEMENTS

$21,581,262

 

 

 

 

 

 

NOTES:

* - COST FOR WATER/SEWER CONNECTIONS NOT INCLUDED

 

 

** - COST FOR WATER/SEWER CONNECTIONS INCLUDED

 

 

 

 

 

The City of Laredo and Webb County received approval from the TWDB Finance and Policy Committee in April 2000 for funding of $14,738,837 for proposed water and wastewater improvements under the EDAP.  Approval of the EDAP funding by the full BOARD is scheduled for July 2000 after the issuance of a FONSI by the Environmental Protection Agency.  The project area includes two planning areas, Mines Road and SH 359, comprised of a total of fifteen (15) economically distressed subdivisions, or colonias.  The colonias are located outside the city limits but are within the City’s ETJ.  An Interlocal Agreement, included in Appendix E, between the City of Laredo and Webb County states both the City and the County find it appropriate that the City assume responsibility for the extension of water and sewer services into the project area.

 

A.      General Project Description

 

The City of Laredo is located in Webb County, Texas directly across of the Rio Grande River (Rio Bravo) from Nuevo Laredo, Tamaulipas, Mexico.  The City and County are proposing a joint colonias improvements project consisting of water and wastewater service to 15 colonias located outside of the City limits but within the City’s ETJ.  The colonias are within the two planning areas of Mines Road and SH 359 as shown in Figure 1, Project Areas Map.  The planning areas consists of the following colonias:

 

Mines Road Planning Area:

 

Los Corralitos

Ranchitos Penitas West

Los Minerales

Antonio Santos

Ranchitos IV / Los Minerales Annex

 

The proposed water distribution improvements for Mines Road consist of 80,000 linear feet of 8-inch water line, 18,000 linear feet of 10-inch water line, one booster station, and a 50,000 gallon ground storage tank.  The City owns a Water Treatment Plant with capacity available to serve the colonia areas.

 

The proposed wastewater collection system improvements for Mines Road consist of 68,500 linear feet of 8-inch gravity sewer, 3 lift stations, 5,200 linear feet of 4-inch force main, 6,350 linear feet of 6-inch force main, and 32 On-Site Sewage Facilities.  A new 0.125 MGD Package Wastewater Treatment Plant is proposed for the Mines Road area.

 

SH 359 Planning Area:

 

Old Milwaukee                                                                                                                                      San Carlos Phase I

Los Altos                                              San Carlos Phase II

Los Tanquecitos I                                  Ranchitos 359 East

Los Tanquecitos II                                Laredo Ranchettes

D-5 Acres                                            Pueblo Nuevo

   

The proposed water distribution improvements for SH 359 consist of 105,500 linear feet of 8-inch water line, 51,000 linear feet of 12-inch water line, 30,100 linear feet of 16-inch water line, a 250,000 gallon elevated storage tank, a 200,000 gallon ground storage tank and booster station.  The City owns a Water Treatment Plant with capacity available to serve the colonia areas.

 

The proposed wastewater collection system improvements for SH 359 consist of 98,800 linear feet of 8-inch gravity sewer, 6,500 linear feet of 12-inch gravity sewer, 24,150 linear feet of 15-inch gravity sewer, 3 lift stations, 2,200 linear feet of 3-inch force main, and 11,500 linear feet of 6-inch force main.  Wastewater flows generated by colonias will be conveyed to the City of Laredo’s proposed Chacon Creek Interceptor with ultimate treatment at the City's Southside Wastewater Treatment Plant.  A 15-inch trunk line along the Texas Mexican Railroad easement is proposed to convey the wastewater flows from the colonias in the SH 359 study area to the interceptor.  The interceptor began construction in 1999 and is expected to be completed in 2001.  The Southside WWTP has available capacity to serve these colonia areas.

 

The proposed colonia water and wastewater improvements are to be funded by TWDB-EDAP, Webb County and NADBank funds.

 

B.      Compliance with BECC criteria

 

B.1.     General Information

 

The City of Laredo and Webb County Joint Colonias Improvement Project consists of water distribution improvements and wastewater collection and treatment system improvements.  A brief discussion of each is presented below.

 

Water Supply and Treatment.  Adequate facilities are currently not available for the Mines Road and SH 359 planning areas.  The City of Laredo obtains its water supply from the Rio Grande River, and it is the only Certificate of Convenience and Necessity (CCN) holder and nearby supplier of facilities that are adequate to serve the colonias in accordance with state design criteria for water and wastewater systems.  According to the TNRCC, the City's total combined water rights of 40,596 acre-feet/year (approximately 36.24 mgd on an average daily basis) are held under Certificate of Adjudication No. 23-3997A.

 

The City of Laredo has one water treatment facility in operation, the Jefferson Street Water Treatment Plant with a capacity of 60 MGD.  According to the City of Laredo, the water treatment system average daily demand is estimated to be 25 mgd of the 60 mgd capacity (42%) with a maximum daily demand estimated to be 48 mgd.  Based on 36,598 connections, average daily demand is estimated to be 683 gpd/connection with maximum daily demand estimated to be 1,311 gpd/connection.

 

Additional water use information was obtained from the water use survey conducted by the TWDB Planning Division.  The TWDB municipal water use projections include residential, apartment, and commercial flows, while attempting to exclude industrial, agricultural, and irrigation water requirements.  Utilizing population estimates developed from the TWDB most likely series population projections, the City of Laredo population for 1995 was estimated to be 147,286.  This results in the average daily demand of 182 gpcd for the City of Laredo only.

 

Water demand projections represent the minimum state requirements set by TNRCC of 0.6 gpm/connection for average daily flow demands. Water treatment plant capacity requirements are based on a peak daily of 1.6, which is based on an annual basis of the ratio of maximum daily demand to average daily demand determined from the 1995 TNRCC Sanitary Survey of the City's water system.

 

According to data provided by the City of Laredo Utility Department the average monthly residential water consumption per connection is approximately 15,000 gallons. The average household size for the Mines Road and SH 359 planning areas was determined to be 4.55 persons and 4.80 persons, respectively.  This results in an average daily demand of 108 gpcd for the Mines Road planning area and 102 gpcd for the SH 359 planning area.  For the purposes of this study, the average daily residential demand for both planning areas will be based on an average usage of 104 gpcd.

 

Average daily water demand projections and water plant capacity requirements through the year 2016 for the Mines Road and SH 359 planning areas are summarized in Table 2.  The projected average daily water demand and water plant capacity requirements for the Mines Road planning areas for the year 2016 are estimated to be 144,768 (gallons per day) gpd and 231,629 gpd, respectively.  The projected average daily demand and required water treatment plant capacity for the year 2016 for the SH 359 study area are estimated to be approximately 442,728 gpd and 708,365 gpd, respectively.

 

In order to evaluate the City of Laredo’s ability to provide water to the Mines Road and SH 359 planning areas, projections for the In-City water demand were developed.  The City of Laredo water treatment system average daily demand is estimated to be 25 million gallons per day (mgd), which is approximately 42% of the total existing treatment capacity of 60 mgd.  The completion of the improvements to the Jefferson Street Facility will increase the total treatment capacity to approximately 60 mgd.  A summary of average and maximum daily water demand projections through the year 2016 for the City of Laredo and the Mines Road and SH 359 planning areas are summarized in Table 3.  In order to meet the projected water treatment plant requirements of 80 MG for the year 2016, the City plans to expand the plant by an additional 20 mgd.

 

The water system improvements will require an equity buy-in to the existing City of Laredo 60 mgd Jefferson Water Treatment Plant.  The City will also need to acquire an additional 658 Acre-Feet of municipal water rights from the TNRCC’s Rio Grande Watermaster.  The purchase of the equity buy-in for the existing Water Treatment Plant capacity and water rights has been funded by the TWDB.  Furthermore, the TWDB has agreed to purchase existing water rights held by the City of Laredo.  Subsequently, no impact to water transfers or surrounding water supplies would be expected.

 

 

 

 

Table 2

Mines Road and SH 359 Planning Areas

Water Demand Projections (gpd)

City of Laredo - EDAP Facility Plan

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1996

2000

2010

2016

Mines Road Planning Area

Pop.

Average
Daily Demand

Treatment
Required

Pop.

Average
Daily Demand

Treatment
Required

Pop.

Average
Daily Demand

Treatment
Required

Pop.

Average
Daily Demand

Treatment
Required

Los Corralitos

100

10,400

16,640

114

11,856

18,970

146

15,184

24,294

146

15,184

24,294

Ranchitos Penitas West

469

48,776

78,042

537

55,848

89,357

719

74,776

119,642

842

87,568

140,109

Ranchitos IV - Los Minerales

150

15,600

24,960

173

17,992

28,787

218

22,672

36,275

218

22,672

36,275

Antonio Santos

32

3,328

5,325

36

3,744

5,990

50

5,200

8,320

59

6,136

9,818

Ranchitos IV - Los Minerales Annex

86

8,944

14,310

100

10,400

16,640

127

13,208

21,133

127

13,208

21,133

Total

837

87,048

139,277

960

99,840

159,744

1,260

131,040

209,664

1,392

144,768

231,629

SH 359 Planning Area

 

 

 

 

 

 

 

 

 

 

 

 

Old Milwaukee

389

40,456

64,730

389

40,456

64,730

389

40,456

64,730

389

40,456

64,730

D-5 Acres

144

14,976

23,962

163

16,952

27,123

206

21,424

34,278

206

21,424

34,278

Los Altos

504

52,416

83,866

576

59,904

95,846

658

68,432

109,491

658

68,432

109,491

Los Tanquecitos I

302

31,408

50,253

346

35,984

57,574

480

49,920

79,872

547

56,888

91,021

Los Tanquecitos II

86

8,944

14,310

101

10,504

16,806

134

13,936

22,298

134

13,936

22,298

San Carlos I

277

28,796

46,074

312

32,448

51,917

427

44,408

71,053

427

44,408

71,053

San Carlos II (aka San Enrique)

250

26,000

41,600

282

29,328

46,925

394

40,976

65,562

460

47,840

76,544

Ranchitos 359

264

27,456

43,930

302

31,408

50,253

322

33,488

53,581

322

33,488

53,581

Laredo Ranchettes

24

2,496

3,994

29

3,016

4,826

38

3,952

6,323

48

4,992

7,987

Pueblo Nuevo

576

59,904

95,846

658

68,432

109,491

912

94,848

151,757

1066

110,864

177,382

Total

1,391

292,852

468,563

1,583

328,432

525,491

2,093

411,840

658,944

2,323

442,728

708,365

Qave:  Based on 104 gpcd; residential In-City water consumption

 

 

 

 

 

Qmax:  Based on 166 gpcd; 1.6 peaking factor determined from 1995 TNRCC Sanitary Survey of City's water system.

 

 

Table 3

Combined City of Laredo, Mines Road and SH 359 Planning Areas

Water Demand Projections (gpd)

 

 

 

 

 

 

 

 

1996

2000

 

Pop.

Average
Daily Demand

Treatment
Required

Pop.

Average
Daily Demand

Treatment
Required

City of Laredo

    150,201

     27,336,582

     43,738,531

    171,673

     31,244,486

     49,991,178

Mines Road Planning Area

           478

            87,048

          139,277

           549

            99,840

          159,744

SH 359 Planning Area

        1,609

          292,852

          468,563

        1,805

          328,432

          525,491

TOTAL

  152,288

  27,716,482

  44,346,371

  174,026

  31,672,758

  50,676,413

 

 

 

 

 

 

 

 

2010

2016

 

Pop.

Average
Daily Demand

Treatment
Required

Pop.

Average
Daily Demand

Treatment
Required

City of Laredo

    228,780

     41,637,960

     66,620,736

    271,825

     49,472,150

     79,155,440

Mines Road Planning Area

           720

          131,040

          209,664

           795

          144,768

          231,629

SH 359 Planning Area

        2,263

          411,840

          658,944

        2,433

          442,728

          708,365

TOTAL

  231,763

  42,180,840

  67,489,344

  275,053

  50,059,646

  80,095,434

 

 

 

 

 

 

 

City of Laredo:

 

 

 

 

 

 

Qave:  Based on 182 gpcd; System-wide water consumption

 

 

 

Qmax:  Based on 291 gpcd; 1.6 peaking factor

 

 

 

 

 

 

 

 

 

 

 

Mines Road and SH 359:

 

 

 

 

 

 

Qave:  Based on 104 gpcd; residential water consumption

 

 

 

Qmax:  Based on 166 gpcd; 1.6 peaking factor

 

 

 

 

 


Water Distribution.  The water distribution improvements consist of extending City of Laredo waterlines to the colonias and providing new water distribution systems to both planning areas.  Each planning area is discussed in detail below.   

 

Mines Road – Water Distribution

 

Proposed improvements to provide water service to the Mines Road planning area include the construction of a water distribution system within each of the colonias.  Table 4 shows the projected construction costs for the water distribution system within each individual colonia with a total projected construction cost estimated to be approximately $739, 575.

 

The City of Laredo water distribution system is to be expanded to the planning area by extending a 10-inch waterline along FM 1472 from La Bota to FM 3338.  The 10-inch line would supply two 8-inch lines connected to the distribution system for the colonias.  One 8-inch line would extend along FM 3338 from FM 1472 to Ranchitos Penitas West.  The other 8-inch line would extend along FM 1472 from FM 3338 to Los Minerales and the surrounding colonias.  A 50,000 gallon ground storage tank and booster station are proposed for the Mines Road area for pressure maintenance.  Table 5 shows the costs to extend the City of Laredo waterlines to serve the Mines Road planning area is approximately $1,103,550.  The proposed water distribution improvements are shown in Figure 2 (Mines Road.)

 

SH 359 – Water Distribution

 

Proposed improvements to provide water service to the SH 359 planning area include the construction of a water distribution system within each of the colonias.  Table 6 shows the projected construction costs for the water distribution system within each individual colonia to be approximately $1,902,972.

 

The proposed colonia distribution systems would be supplied using City water by extending a water line from the City limits to Pueblo Nuevo.  These water line extensions, as shown in Figure 3, would include a 16-inch water line from the City's South Elevated Storage facilities to the Old Milwaukee colonia.  The remainder of the colonias would be served through a series of proposed 12-inch water lines. 

 

The water modeling effort completed by TC&B also recommended the following facilities be included in the proposed water improvements in order to adequately serve the colonias within the SH 359 planning area.  These improvements include a 200,000 gallon ground storage tank and a 250,000 gallon elevated storage tank, combined with a booster pump station located at D-5 Acres, with at least two pumps having a combined capacity of 1,000 gpm, and rated at 195 feet of total dynamic head.  The total estimated construction costs of the proposed extensions and facilities is estimated to be $2,548,350 as itemized in Table 7 (Costs are exclusive of land acquisition costs.)

 

The water distribution improvements are shown in Figure 4 (SH 359.)

 

Table 4

Mines Road Planning Area

Estimated Construction Cost - Colonia Water Distribution Improvements

 

 

 

 

 

 

Colonia Project
Area

Description

Estimated
Quantity

Unit

 Unit
Price

Total
Cost

Los Corralitos

8-Inch PVC

2,800

LF

 $   12.00

 $           33,600

 

8-Inch Gate Valve

2

LF

 $      450

 $                900

 

8" x 10" Tee

1

EA

 $      500

 $                500

 

Fire Hydrant Assembly

6

EA

 $   1,800

 $           10,800

 

Service - 3/4"

12

EA

 $      275

 $             3,300

 

Service - 1"

10

EA

 $      300

 $             3,000

 

Flush Valve

1

EA

 $      150

 $             1,250

 

8-Inch Cap

2

EA

 $      175

 $                350

 

Fittings (Bends, tees, crosses)

2

EA

 $      350

 $                700

Subtotal

 $         54,400

Ranchitos Penitas West

8-Inch PVC

28,050

LF

 $   12.00

 $         336,600

 

8-Inch Gate Valve

20

LF

 $      450

 $             9,000

 

Fire Hydrant Assembly

25

EA

 $   1,800

 $           45,000

 

Service - 3/4"

90

EA

 $      275

 $           24,750

 

Service - 1"

57

EA

 $      300

 $           17,100

 

Flush Valve

3

EA

 $   1,250

 $             3,750

 

8-Inch Cap

3

EA

 $      175

 $                525

 

Fittings (Bends, tees, crosses)

13

EA

 $      350

 $             4,550

Subtotal

 $       441,275

Los Minerales

8-Inch PVC

8,200

LF

 $   12.00

 $           98,400

 

8-Inch Gate Valve

9

LF

 $      450

 $             4,050

 

Fire Hydrant Assembly

10

EA

 $   1,800

 $           18,000

 

Service - 3/4"

28

EA

 $      275

 $             7,700

 

Service - 1"

14

EA

 $      300

 $             4,200

 

Flush Valve

2

EA

 $   1,250

 $             2,500

 

8-Inch Cap

3

EA

 $      175

 $                525

 

Fittings (Bends, tees, crosses)

4

EA

 $      350

 $             1,400

Subtotal

 $       136,775

Antonio Santos

8-Inch PVC

1,400

LF

 $   12.00

 $           16,800

 

8-Inch Gate Valve

2

LF

 $      450

 $                900

 

Fire Hydrant Assembly

4

EA

 $   1,800

 $             7,200

 

Service - 3/4"

8

EA

 $      275

 $             2,200

 

Service - 1"

6

EA

 $      300

 $             1,800

 

Flush Valve

1

EA

 $   1,250

 $             1,250

 

8-Inch Cap

1

EA

 $      175

 $                175

 

Fittings (Bends, tees, crosses)

2

EA

 $      350

 $                700

Subtotal

 $         31,025

Ranchitos IV

8-Inch PVC

4,600

LF

 $   12.00

 $           55,200

Los Minerales Annex

8-Inch Gate Valve

3

LF

 $      450

 $             1,350

 

Fire Hydrant Assembly

6

EA

 $   1,800

 $           10,800

 

Service - 3/4"

14

EA

 $      275

 $             3,850

 

Service - 1"

7

EA

 $      300

 $             2,100

 

8-Inch Cap

2

EA

 $      175

 $                350

 

Fittings (Bends, tees, crosses)

7

EA

 $      350

 $             2,450

Subtotal

 $         76,100

Total Water Improvements

 $       739,575

17% Contingency

 $         125,728

Grand Total Water Improvements

 $       865,303

 

Table 5

Estimated Construction Cost for Mines Road Planning Area

Alternative No. 1 - Water Improvements (Selected Alternative)

 

 

 

 

 

 

Project

Description

Estimated
Quantity

Unit

 Unit
Price

 Total
Cost

La Bota to FM 3338

10-Inch PVC

18,000

LF

 $        14

 $     252,000

10-Inch Water Main Extension

10-Inch Gate Valve

18

EA

 $      700

 $       12,600

 

Booster Station

1

EA

 $  75,000

 $       75,000

 

16-Inch to 10-Inch Reducer

1

EA

 $    1,250

 $         1,250

 

Fire Hydrant Assembly

6

EA

 $    1,800

 $       10,800

 

Air Release Valve

2

EA

 $    1,250

 $         2,500

 

Pipe Casing

3,000

LF

 $        20

 $       60,000

 

Fittings (Bends, tees, crosses)

10

EA

 $      350

 $         3,500

 

Traffic Control Devices

1

LS

 $    7,500

 $         7,500

Subtotal

 $        425,150

FM 3338 to Ranchitos Penitas West

8-Inch PVC

14,000

LF

 $    12.00

 $     168,000

8-Inch Water Main Extension

8-Inch Gate Valve

14

LF

 $      450

 $         6,300

 

8-Inch x 10-Inch Tee

1

EA

 $      500

 $            500

 

Fire Hydrant Assembly

5

EA

 $    1,800

 $         9,000

 

Bore under FM 1472

250

LF

 $      200

 $       50,000

 

Air Release Valve

1

EA

 $    1,250

 $         1,250

 

50,000 GallonGround Storage Facility (including pumps)

1

LS

 $120,000

 $     120,000

 

8-Inch Cap

1

EA

 $      175

 $            175

 

Fittings (Bends, tees, crosses)

7

EA

 $      350

 $         2,450

 

Traffic Control Devices

1

LS

 $    7,500

 $         7,500

Subtotal

 $        365,175

FM 3338 to Los Minerales Annex

8-Inch PVC

21,000

LF

 $    12.00

 $     252,000

8-Inch Water Main Extension

8-Inch Gate Valve

21

EA

 $      450

 $         9,450

 

Fire Hydrant Assembly

5

EA

 $    1,800

 $         9,000

 

Concrete Encasement

1,500

LF

 $        20

 $       30,000

 

Air Release Valve

1

EA

 $    1,250

 $         1,250

 

8-Inch Cap

1

EA

 $      175

 $            175

 

Fittings (Bends, tees, crosses)

11

EA

 $      350

 $         3,850

 

Traffic Control Devices

1

LS

 $    7,500

 $         7,500

Subtotal

 $        313,225

Total Water Improvements

 $     1,103,550

17% Contingency

 $           187,604

Grand Total Water Improvements

 $     1,291,154

 

 

Table 6

SH 359 Planning Area

Estimated Construction Cost - Colonia Water Distribution Improvements

 

 

 

 

 

 

Colonia Project
Area

Description

 Estimated
Quantity

Unit

 Unit
Price

Total
Cost

Old Milwaukee

8-Inch PVC

              8,016

LF

 $       12.00

 $          96,192

 

8-Inch Gate Valve

                     8

EA

 $          450

 $            3,600

 

8-Inch x 16-Inch Tee

                     1

EA

 $          750

 $               750

 

8-Inch x 12-Inch Tee

                     1

EA

 $          500

 $               500

 

Fire Hydrant Assembly

                   16

EA

 $       1,800

 $          28,800

 

Service - 3/4"

                   45

EA

 $          275

 $          12,375

 

Service - 1"

                   18

EA

 $          300

 $            5,400

 

Flush Valve

                     2

EA

 $          500

 $            1,000

 

8-Inch Cap

                     2

EA

 $          175

 $               350

 

Fittings (Bends, tees, crosses)

                     7

EA

 $          350

 $            2,450

 Subtotal

 $        151,417

D-5 Acres

8-Inch PVC

              4,340

LF

 $       12.00

 $          52,080

 

8-Inch Gate Valve

                   11

EA

 $          450

 $            4,950

 

8-Inch x 16-Inch Tee

                     1

EA

 $          750

 $               750

 

8-Inch x 12-Inch Tee

                     2

EA

 $          500

 $            1,000

 

Fire Hydrant Assembly

                     7

EA

 $       1,800

 $          12,600

 

Service - 3/4"

                   25

EA

 $          275

 $            6,875

 

Service - 1"

                     9

EA

 $          300

 $            2,700

 

Flush Valve

                     2

EA

 $          500

 $            1,000

 

8-Inch Cap

                     2

EA

 $          175

 $               350

 

Fittings (Bends, tees, crosses)

                     6

EA

 $          350

 $            2,100

 

Pipe Casing

125

LF

 $            16

 $            2,000

 Subtotal

 $          84,405

Los Altos

8-Inch PVC

              9,500

LF

 $       12.00

 $        114,000

 

8-Inch Gate Valve

                   13

EA